9&20 Milling and Paving

PROJECT UPDATE:

Beginning on July 8th NYSDOT’s contractor will begin milling Rt. 9 & 20 from Rt. 9J to just west of Rt. 4. Milling is expected to take six days. After milling has been completed, there may be a day or two of pavement repairs. Once the milling / repairs are completed, the contractor will begin paving. Paving is expected to take six days.

The following sideroads will also be milled and paved to the existing pavement joint on these sideroads.

  1. Lakeview
  2. Hillview
  3. Sherwood
  4. Ridge
  5. Old Troy

There will be daily lane closures with flaggers at intersections within our work limits Monday through Friday 6 AM to 6 PM. Access to businesses and residences will be maintained, but please be advised that there may be delays of up to five minutes during the milling operation and up to 15 minutes during the paving operation to allow the new pavement to cool.

All the above is of course weather dependent.