Paving Notice - Week of July 31st

The paving contractors will be back on Monday, July 31st to resume paving.  Below is a list of the anticipated roads that we will be working on (not in order of schedule).

Road work is typically scheduled between 6AM - 8PM to provide the contractor adequate time to prep the roads without obstacles.

Week of July 31st:

Will complete Paving on the following roads:

  • Denise Court;
  • Donnelly Drive;
  • Michelle Drive;
  • Flora Circle;

Will begin milling the following roads:

  • Southern Ave;
  • Spring Ave West;
  • Maryland Ave West;
  • Madison Ave West;
  • Servis Place;
  • Western Ave;
  • Mohawk Ave;
  • Washington Ave West.

Upcoming:

  • Tampa Avenue;
  • New Jersey/Ontario Ave (and Ontario Ave Basketball Court);
  • Clinton Street;
  • Muriel Avenue;
  • New York Avenue;
  • Pennsylvania Avenue;
  • Rhode Island Avenue;
  • Park Avenue.

Important Notice to Residents of these streets:

It is essential that residents cooperate by parking all vehicles off the roadway during paving operations and any residents that use off-street parking spaces must park 2 ft. behind the curb line

Please refrain from putting loose piles or bags of brush in the roadway as it will slow down paving operations.

There may be minor delays but we will make every effort to accommodate any and all reasonable requests for assistance in leaving or entering your property.  We ask that you please plan to use alternate routes during paving operations and allow for extra time if possible. 

As always, we appreciate your anticipated cooperation and apologize for any inconvenience this may cause you.  We apologize for the short notice this time; however, the weather conditions sometimes reduce our ability to plan our jobs in our usual efficient manner.

It is important to note that this is only the start of the paving operations that will take place this year.  We have several other large scale paving projects that will take place in the upcoming months; however, once we receive firm dates from our contractor we will be sure to notify residents in advance.

If you have any questions and/or concerns, please contact the  Highway Department office 518-477-7296.